About whether it can be extended PPH storage tank Of course, the answer to this question is yes. For the special PPH storage tank of the equipment, our normal operation will certainly improve its service life, and good maintenance and overhaul can improve its service life to a certain extent. PPH winding tank
1. The first is the basic requirements for the storage tank of the PPH device. The horizontal surface of the platform can accept the corresponding pressure. If it is a steel structure, the gap cannot be too large, and it needs to be covered with wood or iron. Check whether there are nails and other sharp objects on the board to avoid damaging the water tank, or use concrete as the base. Smooth lubrication is required. For ordinary mud, wood bottom can be used to increase the pressure.
2. When PPH storage tank stores chemicals, after the storage tank arrives at the site, there must be a good drainage channel and dilution system or leakage alarm system around the site.
3. During the installation of 20 m3, 30 m3 and 50 m3 large storage tanks, special attention should be paid to safety and cranes should be used as far as possible.
4. After the installation of PPH storage tank, the sealing performance of the interface should be stopped in time before use. If conditions permit, add liquid outside the interface to check whether there is leakage. It is contained in chemical liquid storage tank, and it is recommended to conduct water leakage test to prevent the formation of a large amount of liquid loss, which does not require the loss of human, material and financial resources.
5. The pipe connected to the flange at the bottom of PPH tank should be perpendicular to the barrel wall. It is recommended to use soft joint to avoid uneven shrinkage of the barrel wall after filling liquid, which will lead to damage and leakage of the joint, thus damaging the joint flange, which will directly affect the overall life of the barrel.
6. When the liquid inlet is higher from the tank bottom, the liquid inlet on the tank wall should be bent to make the incoming liquid fall and reduce the direct impact of liquid on the tank bottom.
7. When the mixer and other heavy secondary equipment are installed on the tank, or when personnel need to work on the tank top and the tank top cannot bear the weight of personnel, please make another mixing channel steel support, steel pipe ladder and fence, and pay attention to the safety of operation.
8. In the process of consumption or technical operation, if the liquid level cannot be checked in time, a level gauge or sensing device can be installed, and the tank manufacturer can be contacted to install an overflow valve to prevent the liquid from overflowing from the manhole, causing unnecessary losses and injuries.
9. When the liquid in and out of the storage tank site is large, technicians need to be arranged to install the corresponding outlet pipe in time.